Landed Cost: The Formula That Turns a 6% Saving Into a 4% Loss

A new supplier quotes $9.20 against your incumbent's $9.80. Six percent cheaper on a part you buy 400 of a year. Easy call.

It isn't, and the arithmetic takes about a minute.

The equation

landed = (unit × Q)
       + freight
       + (tooling / lifetime_Q) × Q
       + carrying × (MOQ − Q) × unit × (holding_years / 2)
       + terms_cost

Only the first term appears on the quote. The other four decide the answer.

Carrying cost is conventionally 20–25% a year of the value sitting on your shelf — capital, space, insurance, obsolescence. Use 22% if you have no better number; being roughly right beats ignoring the term.

Terms cost is the working capital the payment terms take from you:

terms_cost = spend × annual_capital_rate × (their_days − your_baseline_days)/365

Worked, at Q = 400/year

Term Incumbent New supplier
Unit × Q 9.80 × 400 = $3,920 9.20 × 400 = $3,680
Freight included $340
Tooling ($1,800 / 5,000 lifetime) × 400 $0 (owns fixture) $144
MOQ carry — MOQ 1,000, so 600 extra held ~0.75 yr avg $0 0.22 × 600 × 9.20 × 0.75 = $911
Terms — net-15 vs net-45, 12% capital $0 3,680 × 0.12 × (30/365) = $36
Landed $3,920 $5,111

The 6% saving is a 30% increase. Three of the four extra terms would be invisible in a spreadsheet with one column called "price".

The break-even question worth asking instead

Rather than comparing totals, solve for the quantity where the cheaper unit price finally wins:

Q* = (freight + tooling_share + MOQ_carry) / (unit_incumbent − unit_new)
   = (340 + 144 + 911) / (9.80 − 9.20)
   = 1,395 / 0.60
   = 2,325 units/year

You buy 400. You would need to buy 5.8× more before this supplier is cheaper. That's not a negotiation position, it's a different business — and it's a far more useful thing to know than "6% cheaper".

Lead time doesn't belong in the equation

Resist converting it to money. A part arriving in three weeks instead of six is worth a great deal on a job with a customer promise attached and almost nothing on a restock. Converting it to a single currency figure hides that difference behind a number that looks objective.

Compare it as its own column and decide deliberately which kind of job this is. Some jobs are cost jobs, some are date jobs. The failure is letting a sheet sorted by unit price decide silently.

How this gets solved

Every term above except unit price normally lives somewhere the comparison can't see it: freight in an email, MOQ in a PDF footnote, terms in the supplier's boilerplate.